The short version
- The proposal: TerraWatt wants to buy the former Alton Steel mill at 5 Cut Street, tear down the mill buildings, and build the "Riverbend Technology Center." It would draw power from the grid and be built in 200-megawatt blocks, up to 1 gigawatt in all. The sale depends on Alton rezoning the land, and no application has been filed yet.
- The pushback: Hundreds of people turned out for TerraWatt's Oct. 27 open house, many of them to protest, and most of the public comments at City Council since have been against the project. On Monday, Nov. 23, Alton's Committee of the Whole takes up a proposed temporary moratorium on data center applications.
- The regional signal: On Nov. 3, voters in four Granite City-area townships rejected advisory questions on permitting data centers by margins of 74% to 83%. Those votes weren't about Alton and don't bind anyone. They were part of a national pattern, though: voters chose limits in 40 of the 41 data center measures on ballots across the country that day.
A gigawatt-scale proposal on the Mississippi River is going to dominate Riverbend conversation for months, online and at council meetings. Much of what's being shared is either the developer's own numbers or protest-sign slogans. This is an attempt to separate what's been claimed, what's been checked, and what hasn't been decided.
This builds on our earlier data center coverage, including Part 3 of our data center series and our explainer on data centers, power plants and Ameren.
What's being proposed
The site. Alton Steel shut down in January 2026, and 253 people lost their jobs. Steel had been made on that land for more than a century. In its earlier life as Laclede Steel, the mill once employed about 4,000 people. Alton Steel's board says it chose TerraWatt's offer as the best way to get value out of the property and pay off the company's remaining creditors.
The developer. TerraWatt is based in Carson City, Nevada. It's the same company behind the $3.1 billion, 120-megawatt data center approved for the old Famous-Barr warehouse next to The Armory in Midtown St. Louis. That project is now tied up in dueling lawsuits (more below).
The plan, as TerraWatt describes it:
- Demolish about 1.26 million square feet of mill buildings and pay for the cleanup, including asbestos removal under Illinois EPA and OSHA rules.
- Build in 200-megawatt "blocks." The first would go where the furnaces and rolling mill stand now, and up to five blocks could follow, but only as Ameren Illinois confirms it can deliver the power.
- Power would come entirely from the Ameren grid, through a substation and connection that TerraWatt pays for. There would be no gas-fired plant on site, only diesel backup generators.
- Timeline: demolition in 2027, construction of the first block from late 2027 into early 2029, and full operation around 2031.
- No local tax incentives requested. The site sits in the Riverfront TIF district, which expires in December 2029, and TerraWatt says it won't use TIF money.
- Construction under a project labor agreement, a commitment to stay at least 20 years, and a "carbon-neutral" pledge. The project site doesn't explain how carbon neutrality would be achieved.
What it needs before anything happens: Alton must issue a use determination and rezone the land to a planned industrial district, with Plan Commission and City Council hearings. Ameren must complete a study of the site. Illinois EPA must issue permits for the generators and for stormwater during construction. The sale wouldn't close until 2027, and only if all of that clears.
Checking the developer's numbers
TerraWatt's project website, riverbendalton.com, is detailed. It also calls every figure an estimate, not a guarantee. Here's how the main claims hold up:
| Claim | What we found | Status |
|---|---|---|
| The site pays $98,736 a year in property tax today | Consistent with the developer's release and TV coverage. We haven't checked the county tax records. | Unconfirmed. |
| One block would pay about $17.2 million a year in property tax | The site's header calls this the first full year figure. Its FAQ calls it an average over the first 10 years, with lower early years because of the TIF. These aren't the same claim. | Unconfirmed. |
| About $9.9M a year to Alton School District 11 and $4.2M a year to the city | These come from the same projection. The other taxing bodies get no dollar figure. | Unconfirmed. |
| About 4,500–4,800 construction jobs, 50 permanent jobs per block averaging $90K+ | Both construction figures appear on the site. The permanent count matches what data centers generally employ, which is very few people per megawatt. | Developer claim |
| Water use of about 400,000 gallons a year, versus the mill's ~178 million | Plausible if it uses closed-loop cooling without evaporation, as the company says. That kind of design usually trades water for more electricity. | Developer claim. |
| About 42 dB at the nearest homes, versus 90 dB at the mill | The 90 dB number is measured inside the old mill, and 42 dB is measured at homes more than 250 feet away, so those aren't the same comparison. Constant cooling-fan hum is the top complaint near data centers elsewhere. | Developer claim, apples to oranges. |
| No effect on residential electric bills | Illinois is still writing its rules on this. The ICC approved a large-load tariff for ComEd in northern Illinois and opened a broader investigation into protecting other customers. We couldn't find an equivalent Ameren Illinois tariff yet. | Unconfirmed |
The tax figures are the strongest argument for the project, and they're also the ones the city most needs an independent review of. The city has considered hiring an outside consulting firm to review the project's impact. On Nov. 9, the council held that consulting agreement over for later action instead of approving it.
What people are saying
The city. Mayor David Goins has said he's open to exploring a reuse of the vacant mill, given the lost jobs and tax base. The city has also said publicly that residents' concerns about water, electricity, noise, traffic and neighborhood character "deserve clear, evidence-based answers." It has stressed that no permit or zoning application has been filed and that nothing has been approved. City officials have said they would reject any payments or gifts from developers.
Opponents. The line for the Oct. 27 open house at The Wedge wrapped around the building, and some people waited close to an hour. Protesters stood outside with "No Data Center" signs. At the City Council meeting the next night, about 20 people spoke against the project, during more than two and a half hours of public comment. More residents spoke against it at the Nov. 9 Committee of the Whole and again at the Nov. 12 council meeting. That made three meetings in a row dominated by opposition. Their concerns include:
- noise and health
- electric rates and grid reliability
- water and the river
- the small number of permanent jobs compared with the mill
- property values
- distrust of a developer already in court in St. Louis
Some also worry that once the land is rezoned, the city loses leverage over what gets built. A Change.org petition asks the city to deny the project.
Supporters and the undecided. They've been quieter, but they're there. Some open-house attendees said they were keeping an open mind. The case for the project goes like this: a 381-acre brownfield on the river is hard to fill, cleanup costs are high, the mill isn't coming back, and an idle site pays very little in taxes.
The developer. TerraWatt's local partner said the company was "in listening mode" at the open house and would come back with answers. Its community survey is still open.
The Alton moratorium
At the Nov. 12 City Council meeting, Alderwoman Martha Pfister introduced a resolution to start an ordinance "imposing a temporary moratorium on the acceptance and approval of applications related to data centers." She said she had printed the resolution "months ago" but hadn't thought it was needed until now.
Here's the process from there:
- Mon., Nov. 23: The Committee of the Whole considers the resolution.
- If it advances: It goes to the full City Council later that week.
- Final approval: It comes back as a written ordinance for a final vote at a future meeting.
So even a quick "yes" wouldn't put a moratorium in place by Thanksgiving.
Not every council member is ready to decide on the project itself. Alderwoman Stephanie Elliott suggested Alton officials visit communities that already have data centers. She wants to talk with the people who made the decisions there, both those who are glad they did and those who aren't. "All I'm hearing is, 'We don't want it,'" she said, "but when you make a decision about anything, you still have to listen to both sides."
A moratorium wouldn't ban data centers. It would pause applications while the city writes rules for them. Nearby Godfrey already has one. Its Village Board approved a pause of up to 180 days in January 2026. In August, the board extended it another six months, saying it needed more time to study possible regulations. That pause now expires Jan. 31, 2027. That's common across the country: cities and counties from Plainfield to Oklahoma City have adopted or extended similar pauses this year.
Meanwhile, in the Granite City area
On Nov. 3, four townships that overlap Granite City voted on a non-binding question: "Shall the construction and operation of new data centers be permitted in [Township] Township?" The results:
| Township | No | Yes |
|---|---|---|
| Chouteau | 83.3% (1,817) | 16.7% (365) |
| Nameoki | ~77.9% (2,117) | ~22.1% (602) |
| Venice | ~75.9% (978) | ~24.1% (311) |
| Granite City | 74.4% (5,703) | 25.6% (1,959) |
Unofficial results with all precincts reporting. Percentages are rounded, and the official canvass may differ slightly.
Residents put the questions on the ballot by petition. The best-known face of that effort is Heather Groetecke, a lifelong Granite City resident. She has said she started gathering signatures after officials never answered her questions about environmental hazards, and she has led the local conversation against data centers ever since. The petition drive followed a busy first half of 2026 in Granite City. Developers were scouting land, residents packed forums and zoning meetings, and the city discussed two possible sites along the Route 3 industrial corridor. City officials have since said the Granite City project is tabled, not dead. Mayor Mike Parkinson has said repeatedly that no company has made the city an offer. The same voters also rejected selling the township's sewer system (Special Service Area No. 1) to a private company.
What these votes are and aren't: They're advisory, so they ban nothing and don't bind any official. They weren't about Alton, and Alton voters didn't weigh in. But they're the clearest measure yet of how Madison County residents feel. And they weren't unusual. Of the 41 local data center measures on the ballot nationally on Nov. 3, 40 went toward limits. In Illinois, Joliet Township voted 79% no, Bloomington backed an advisory moratorium, and Morgan County voted for restrictions.
What's not true (or not established)
- "The city already approved it." No application has been filed, and nothing has been approved.
- "The townships voted to ban data centers." The questions were advisory and changed no laws.
- "TerraWatt is an EV-charging company from San Francisco." At least one widely shared national article mixed up TerraWatt with TeraWatt Infrastructure, a different company that builds EV-charging networks. Those two names are similar enough that the developer is in a trademark dispute with another company called TERRAWATT.
- "Your electric bill will definitely go up." No evidence either way yet. That depends on rules Illinois regulators haven't finished and on an Ameren study that hasn't been done.
About the St. Louis lawsuits
TerraWatt's Midtown St. Louis project won a city permit. In August, environmental, neighborhood and labor groups sued to overturn that approval. In September, TerraWatt co-founder David Lambiaso sued the city's Board of Adjustment over two permit conditions he called illegal and "practically impossible." Last week a judge sided with the developer on a renewable-energy condition, though the city's broader requirement remains: data centers must work toward getting 50% of their power from renewables within five years.
Supporters see a developer protecting an approved project. Opponents see a preview of how TerraWatt would treat conditions Alton puts on it. Both readings are on the table.
What we don't know yet
- Whether TerraWatt will file an application at all if a moratorium passes, and when.
- What Ameren's study finds about available power, and who pays for any upgrades beyond the site itself.
- Independent tax figures. The header-versus-FAQ discrepancy on the $17.2 million needs an answer.
- Who the eventual tenant would be. Developers often build first and lease later, and the tenant decides how hard the facility runs.
- How "carbon-neutral" would be measured or enforced.
- What cleanup the site actually needs. Steelmaking sites can carry contamination beyond asbestos, and the details would show up in Illinois EPA filings.
Why it matters here
Alton lost a 253-job employer in January, and the site is now a large, empty liability. The tax numbers TerraWatt is offering would be significant for District 11 and the city, if they hold up. On the other side are real questions about noise, power and a 30-year bet on one industry. All of it would be decided by a City Council that hasn't seen an application yet.
For the rest of Madison County, this is the first gigawatt-scale proposal to get this far, and it's arriving right after voters in four townships said no. However Alton handles it, whether through a moratorium, a negotiated set of conditions, or a rejection, it will probably become the template other towns in the county use.
What to watch
- Mon., Nov. 23: Alton's Committee of the Whole considers the moratorium resolution. Check the city's agenda for the time.
- Later that week: If the committee advances it, the full City Council votes on the resolution. A final ordinance vote would come at a later meeting.
- The next City Council meeting after that: a possible full vote on the moratorium.
- The consulting agreement the council held over on Nov. 9: whether it comes back, who the firm is, and what it's asked to review.
- Any filing by TerraWatt, including a zoning application, a Plan Commission date, or an Illinois EPA permit application.
- The ICC's large-load investigation and any Ameren Illinois data center tariff. That's where the "will my bill go up" question actually gets decided.
- The Midtown St. Louis lawsuits.
Sources
- Riverbend Technology Center (TerraWatt project site, dated Oct. 21, 2026): https://www.riverbendalton.com/
- First Alert 4, "Data center proposed for former Alton Steel site," Oct. 21, 2026: https://www.firstalert4.com/2026/10/21/data-center-proposed-former-alton-steel-site/
- First Alert 4, "Alton Steel CEO names TerraWatt as proposed buyer," Oct. 22, 2026: https://www.firstalert4.com/2026/10/22/alton-steel-ceo-names-terrawatt-proposed-buyer-mill-site/
- KSDK, "Massive data center campus may soon take over Alton Steel's former plant": https://www.ksdk.com/article/money/economy/energy/massive-alton-data-center-campus-take-over-alton-steel-former-plant/63-3de048e0-5671-47fe-b74b-154b77dd2a1f
- St. Louis Magazine, "Former Alton Steel property would become a data center under TerraWatt plan": https://www.stlmag.com/business/terrawatt-pitches-data-center-for-alton-steel-property/
- Data Center Dynamics, "Gigawatt-scale data center proposed for steel mill in Illinois," Oct. 23, 2026: https://www.datacenterdynamics.com/en/news/gigawatt-scale-data-center-proposed-for-steel-mill-in-illinois/
- RiverBender, open house coverage, Oct. 28, 2026: https://www.riverbender.com/news/details/terrawatt-receives-alton-feedback-before-finalizing-data-center-plans-97857.cfm
- RiverBender, "Protesters Gather Outside Open House": https://www.riverbender.com/news/details/protesters-gather-outside-open-house-on-proposed-alton-data-center-97854.cfm
- RiverBender, "Alton Leaders Hear Overwhelming Opposition," Oct. 30, 2026: https://www.riverbender.com/news/details/alton-leaders-hear-overwhelming-opposition-to-data-center-proposal-97943.cfm
- RiverBender (Dalton Brown), "Alton To Consider Data Center Moratorium As Public Opposition Continues," Nov. 16, 2026: https://www.riverbender.com/news/details/alton-to-consider-data-center-moratorium-as-public-opposition-continues-98376.cfm
- RiverBender, "Alton Considering Consulting Firm For Data Center Impact Review," Nov. 6, 2026, and "Alton Lays Over Data Center Consulting Agreement," Nov. 9, 2026 (search RiverBender by title)
- River County News, "Moratorium on data centers referred to Alton Committee of the Whole," Nov. 12, 2026: https://rivercountynews.com/2026/11/12/moratorium-on-data-centers-referred-to-alton-committee-of-the-whole/
- First Alert 4, open house coverage, Oct. 28, 2026: https://www.firstalert4.com/2026/10/28/alton-residents-pack-open-house-about-possible-data-center-former-steel-mill/
- RiverBender, "Godfrey Places 180-Day Pause On Data Center Applications": https://m.riverbender.com/news/details.cfm?id=90093
- Capitol Fax, roundup of local data center referendums, Nov. 6, 2026: https://capitolfax.com/2026/11/06/voters-overwhelmingly-reject-data-centers-in-local-referendums/
- Chronicle Media, Madison County election results: https://chronicleillinois.com/election/historic-democratic-wave-sweeps-harriss-out-of-26th-senate-schmidt-from-114th-house/
- Data Center Dynamics, local moratoria and restrictions voted in across the US: https://www.datacenterdynamics.com/en/news/local-data-center-moratoria-limits-and-restrictions-voted-in-across-the-us/
- St. Louis Public Radio, "Developer behind $3.1B Midtown data center sues St. Louis," Sept. 17, 2026: https://www.stlpr.org/news-briefs/2026-09-17/developer-st-louis-data-center-armory-files-lawsuit-against-city
- FOX 2, "Judge removes renewable energy requirement for Midtown data center": https://fox2now.com/news/missouri/judge-removes-renewable-energy-requirement-for-midtown-data-center/
- St. Louis Magazine, TerraWatt trademark dispute: https://www.stlmag.com/news/terrawatt-vs-terrawatt-trademark-dispute/
- E&E News, "Illinois moves to blunt rate hikes tied to data centers": https://www.eenews.net/articles/illinois-moves-to-blunt-rate-hikes-tied-to-data-centers/
- Wikipedia, Alton Steel (closure date and job count, cross-checked with KSDK): https://en.wikipedia.org/wiki/Alton_Steel
- Change.org, "Stop Data Center Development in Madison County, Illinois": https://www.change.org/p/stop-data-center-development-in-madison-county-illinois
- RiverBender, Slusser on data centers after touring a Google facility: https://m.riverbender.com/news/details.cfm?id=89985